‘Repairs on Lagos-Ibadan expressway 32% completed’

The engineer supervising the reconstruction/rehabilitation works on the Lagos-Ibadan Expressway, Mr. Kayode Ibrahim, said the project was 32 per cent completed.

Ibrahim told the News Agency of Nigeria on Monday that work had been completed on one section of the Long Bridge and on various critical sections.

resolution_technologies_app_wetinhappen_nigeria-Uyo_download_partner_affiliates

Section one of the projects is from Ojota in Lagos to Sagamu Interchange and is being handled by Julius Berger.

He said more warning signs and crash barriers had been deployed to the highway to ensure a free flow of traffic and check accidents.

“We will complete the repair of the Long Bridge by December 15 and we will complete all palliatives to make the road motorable before the Yuletide.

Trending Now!  Boko Haram Has Abducted Over 1,000 Children In Nigeria Since 2013 – UNICEF

“The entire project is 32 per cent completed. We have done earthworks, laid asphalt and base course, done culverts and drains on various changes between Redeemed Camp and the Sagamu Interchange.

“We have constructed trapezoidal drains, rectangular drains and retaining walls on various portions and also laid polymer modified asphalt on various shoulders. We are working massively on various portions,” Ibrahim said.

Copyright PUNCH.               
All rights reserved. This material, and other digital content on this website, may not be reproduced, published, broadcast, rewritten or redistributed in whole or in part without prior express written permission from PUNCH.

Contact: editor@punchng.com

Trending Now!  Croatia Coach Confirms Modric, Rakitic For Peru, Mexico Friendlies; Lovren Out

 

The post ‘Repairs on Lagos-Ibadan expressway 32% completed’ appeared first on Punch Newspapers.

Leave a Reply